Additional Material Storage costs are not limited to just critical project delays. Similar to idle labor and equipment costs, additional material storage costs can also result from owner-caused inefficiency, disruptions, and suspensions.
For example, if the contractor is storing structural steel for the project and the start of steel erection was delayed a month, which was the owner’s responsibility, then the contractor may be entitled to recover the additional cost of storing that material for an additional month.